First Xyla on-site, day two

//First Xyla on-site, day two

First Xyla on-site, day two

Here are nine photos from the second day of assembly of the first Unity Home. This Xyla was fully enclosed and weather tight in two days, a day less than our initial estimate.

Unity bundle

Bundles are wrapped to protect them. Then labeled with job name, contents, and weight.

The start of day 2: The crane sets the first wall at 7:30 in the morning

The start of day 2: The crane sets the first wall at 7:30 in the morning

Tight tolerances.

Tight tolerances.

The next panel, roughly 8:15

The next panel, roughly 8:15

Doors are pre-installed in 'mini-panels', which are dropped in place on site.

Doors are pre-installed in ‘mini-panels’, which are dropped in place on site.

ceiling panel

Interior ceiling panels are uninsulated.

tolerances

An example of how tight the tolerances are. The ceiling panel is snug against both the timber and the exterior wall.

Roof panels are flown by crane, just like the walls.

Roof panels are flown by crane, just like the walls.

done in two days

3:00 PM on day two. The weather-tight shell is complete

2017-01-12T13:48:58+00:00 December 7th, 2012|0 Comments